From the week ending November 4, 2016.
Parkade stairwell.

In the last two weeks, the following work on the construction site was ongoing or completed:

  • Forming and concrete pouring for retaining walls and basement interior walls

Scheduled for work for the next two weeks includes:

  • forming and concrete pouring in parking area stairwell
  • installing of weeping tiles
  • installing damproofing
  • backfilling basement area.